Well, I am back and have taken some photos - some explanations.
Today found two more faults........ one maybe more serious than the other.
|
Nail through Rubberseal roof - coming up from Rockwool wall |
Always had a worry about the drains, and today there seems that this worry is confirmed..........
Kevin Edwards told us that he had asked for Building Control to look at the drains when they had been done, back in January, but told us that they were too busy to come out - now wonder if this was true!
The new drain from the en-suite bathroom to master bedroom
|
leaking!!!! |
BUT, good things happening too
|
kitchen floor in process of being levelled |
|
gas pipe for cooker in place |
|
gas supply starting to come into house |
|
gas pipe outside boiler room |
|
floor levelling in second bedroom started |
Rockwool wall - before, and note no DPC.......
The wall cut back for repairs and to place DPC which was missing, however, there was DPC over the new part of the wall that Kevin Edwards had built......
|
nibbled brickwork showing serious damage when the render was removed |
|
DPC now placed under rain stop/drip |