And some pictures of the plastered skylights, and the washbasin in the bathroom
The daily events of the extension and refurbishment of a small mid-20th Century modernist house in East Lothian
Sunday, 28 July 2013
Mixed week - plastering and electrics going on......... and bits of floor levelling taking place
Tuesday, 23 July 2013
Tuesday 23rd July
Bathroom ceiling plastered, skylights in the hall have plasterboard fitted, ready for plastering. Door thresholds in for eventual levelling and screeding of floor.
Heavy downpour of rain this afternoon - revealed joint around rainwater pipes (which run through the house) are leaking as only jointed with putty, and not a hard compound, or a rubber joint - will have to be repaired.........
The other leaking one is in the cupboard where the boiler will be situated.
Meeting with Architect this a.m. towards preparing a legal case against first builder.
Heavy downpour of rain this afternoon - revealed joint around rainwater pipes (which run through the house) are leaking as only jointed with putty, and not a hard compound, or a rubber joint - will have to be repaired.........
This is in the electrical cupboard
The other leaking one is in the cupboard where the boiler will be situated.
Meeting with Architect this a.m. towards preparing a legal case against first builder.
Friday, 19 July 2013
Friday 19th July 2013
Well, back from Mull, where it as cool, to a very hot Haddington. Whilst we have been away plastering has been underway, and electrics. So, the sitting room is plastered, walls and ceiling, the master bedroom ceiling has been plastered too, and some other odd walls. The sun pipes are installed, but not fully functioning yet, as they still have their reflective surface covered, until the bathroom ceilings have been plastered, and then they will be revealed in all their glory.
The electrician's have also been in and started the second fix, and will be back next week to do some more.
The electrician's have also been in and started the second fix, and will be back next week to do some more.
sitting room |
sitting room |
bedroom and inside cupboard |
corner of bedroom window - with shadow gap |
bedroom looking toward the en-suite bathroom |
kitchen, nearly ready for plastering |
Sunday, 14 July 2013
SUNDAY 14th July - Bastille Day
Not much to take photos of. Plasterboard going up slowly, plumbing mostly done; en-suite bathroom about to be tackled; old bathroom almost finished; doors on order, as is a new kitchen sink; and have to buy heated mirrors and electric radiators for the two bathrooms. Maybe the interior will be finished by August! Then the exterior to be finished off - repairs to be made to the exterior render on the school side and the rest of the walls to be rendered.
Will be away for a few days, so hopefully lots of lovely pictures of things that have happened when I return.
Glad to have some hot sunshine and be out in the garden. Builders not so excited by the weather though. Fan's working overtime indoors. But this weekend some of them are soaking up the sun at T in the Park. Hope they have fun.
See you later next week.
Will be away for a few days, so hopefully lots of lovely pictures of things that have happened when I return.
Glad to have some hot sunshine and be out in the garden. Builders not so excited by the weather though. Fan's working overtime indoors. But this weekend some of them are soaking up the sun at T in the Park. Hope they have fun.
See you later next week.
Thursday, 11 July 2013
Thursday 11th July 2013
Plasterboard going up apace - problem sliding window out and back in, so it doesn't catch on the cill; two working toilets; sunpipes starting to put light into bathrooms, although not finished yet. The sun is shining and the men are whistling....... and we are happy!
wall to kitchen where radiator will go |
ceiling in old bathroom - with sunpipe |
pantry ceiling now insulated and walls plastered - the old water tank used to sit above this space with metal bars holding it all together |
header bracket over triple cripple stud to support window/corner of sittingroom |
as above, showing how it catches beam as it goes over window |
interior of above corner |
sitting room plaster boarded |
sitting room showing radiator pipes |
Friday, 5 July 2013
5th July
Wednesday, 3 July 2013
3rd July big windows out and one back in........
Sorry I have not been doing a daily blog, but been away and busy yesterday, and not a lot of photos to show. However, yesterday John and Neil took out one of the big garden windows and the side door to the sitting room, and got it back in again.
Today the second window has come out, the side wall has been removed, and the Marley tiles that formed the original floor covering in that area and had the wall built onto them have been removed. The brickwork has been stabilised and all is ready for the window to go back after lunch beak.
Insulation that ended where the old roof had been cut back has been inserted, the main beams over windows have had 6" nails through into the joists, as they were only held in by nail gun nails, and not through into the joists. The joist hangers have had the correct nails put into them and in all the holes.........
So lots of busyness today and yesterday and it really feels like we are moving towards the finish.
Today the second window has come out, the side wall has been removed, and the Marley tiles that formed the original floor covering in that area and had the wall built onto them have been removed. The brickwork has been stabilised and all is ready for the window to go back after lunch beak.
Insulation that ended where the old roof had been cut back has been inserted, the main beams over windows have had 6" nails through into the joists, as they were only held in by nail gun nails, and not through into the joists. The joist hangers have had the correct nails put into them and in all the holes.........
So lots of busyness today and yesterday and it really feels like we are moving towards the finish.
Space where old roof cut back but insulation not inserted |
the original 6" nails that came through the roof, but not secured to anything |
Insulation now going in and the beam secured to the cross beams |
the door back in situ |
insulation put in |
insulation completed to roof |