Wednesday, 13 February 2013

WEDNESDAY 15th February

No pictures today - or for the next few days - builders off today, working on Saturday instead.  I am away until early next week, when I hope there will be some interesting developments to show you.  Keep looking.

Tuesday, 12 February 2013

TUESDAY - very cold - still looks like a forest of sticks, but look

men on roof, with chain saw

bits that have been cut off the roof

rebuilding the brickwork

still more bits of roof, plus windows

roof cut back 

window out

and more windows out 

waiting for the big beams

Monday, 11 February 2013

MONDAY - WEEK 5 - sunny day, but very cold

bedroom going up
roof beams for bedroom

where the en-suite bathroom will be

Sunday, 10 February 2013

SUNDAY - Team Foley/Le May get stuck into stripping out plasterboard

striker Foley

demo dad

skip girl 1

skip girl 2

demolition dadagain

Chris has nearly got all the plaster off

a wee fire to keep us warm and cheery on a cold Sunday

Friday, 8 February 2013

END OF WEEK 4.........

our bedroom......

showing en suite bathroom!!!

new kitchen and hall


imagine the front door

Mark taking down the ceilings in the sitting room

more bits of frame






Thursday, 7 February 2013

THURSDAY - now starting to look like a house again. I can see the sizes of the kitchen and bedroom. Exciting.

the corner window of the kitchen

through the wall towards the bedroom a forest of beams

the garden looking towards the new bedroom

where the new sliding doors will go and the garden door





Wednesday, 6 February 2013

WEDNESDAY - out all day yesterday, but here are some pics of what has happened today. In the sun - but its very cold.

the remains of the kitchen wall

the kitchen beams

delivery - timbers and boarding

kitchen wall, I think
the other wall where new sliding floor to ceiling doors will go

corner window gone, and .....

glass - for my fusing project

more glass

Monday, 4 February 2013

Week4 - MONDAY - it doesn't look like a lot has happened but the timber kit is being built - foul weather, cold and sleety and windy. Electrics disconnected to house, but nice and cosy in the garage.

this could be the ingress for the telephone cable
how do you get it in and to the other side of the building without disturbing the exterior
probably problem solved
the kit - today's part


the electrics cupboard - all disconnected

except for a light, a socket for the builders and power to the shower (so we can still be clean)





the cable to the garage

its new route into the electrics cupboard